-
Questions about bus garage/maintenance facility answered pdf
(new window)
-
Photo updates: Aug. 31, 4; July 20, 6; June 23, 1; May 18, 5;
Apr. 27, 13; March 23. 10
-
Progress updates: Feb. 16, Jan. 5, Dec. 1, Nov. 18, Sept. 30,
2009
-
Bids awarded for capital project
Capital project almost finished
The $17 million capital project
approved by voters in February, 2008 is coming to a very successful
conclusion.
----- The high school
physical therapy/physical fitness room is now being used by students
and staff and is expected to be open to the public around the first
of the new year.
----- All school buses and equipment are now under cover in the new
garage/maintenance facility. The wash bay is complete and the
maintenance bay is almost complete.
----- The Harry Hoag library/media center is being well used. The
center provides more about 1,700 square feet of additional space
including additional classroom space, and computer lab with 25
computers and a Smartboard.
---- Harry Hoag offices, hallways, and front kiosk are awaiting
finishing touches. The energy efficient windows are in. Still to go
in are trophy cases and a time capsule. The new parking lot
and traffic pattern have improved the flow of traffic and safety for
students.
Photo page update
School board approves addition to capital
project at no cost to public
At its Sept 21
meeting, the board of education approved approximately $1 million in
work to be added to the capital project approved by voters in 2008.
The project addition will update technology infrastructure, and
improve communications, safety and energy efficiency. There will be
no additional cost to taxpayers for these improvements.
The work includes: reconstruction of a fire
access road and two parking areas at Harry Hoag Elementary School;
replacement of entrances, vestibules and doors at Harry Hoag; and
upgrading of the telephone system, control access system and video
surveillance system district-wide. The new technology infrastructure
will incorporate the security and communications systems into one,
bringing the district up to date technology-wise. The current
technology infrastructure is 11-12 years old.
The work is within the guidelines of
what the voters approved in the original scope of the project. In
planning for the original $17.2 million capital project, district
officials prioritized items, and obtained estimates for those items.
Based on those initial estimates, they removed various items from
the project. The items included in this next phase are those
initially deleted from the original project.
The $1 million became available because:
• capital project bids came in lower than expected,
• project plans were so well drafted the district did not have to
use very much of funds set aside for contingency,
• the project was very well managed and contractors stayed on or
below budget
• by borrowing through the Dormitory Authority of the State of New
York, the district was able to save a significant amount of money on
borrowing costs.
Formal plans for the work will be
drawn up and the plans will be submitted to the State Education
Department for approval. After state approval, the work will be put
out for bid. “The idea is to spend up to the exact bond amount as
you can. Anything you don’t spend you will have to give back and
your state aid will be reduced as well. This new work will give us
full value for the amount approved by taxpayers,” said District
Business Manager Carl Rockefeller.
August 31 ( sign, bus garage, traffic island,
Hoag library,
Hoag front, new windows)
  
  
August 4 (bus garage, Hoag front, new classroom
windows, playground)
  
  
July 20 ( bus garage, Hoag front, high school
addition)
  
July 6 (high school addition, Hoag front, bus
garage, Hoag interior)
  
  
June 23
The capital project is right on schedule. The
new playground should be completed by mid-July, the bus garage
should ready for use by the start of the new school year, as will
new rooms at Harry Hoag and the high school addition. An open house
and dedication will be held in the fall. Photos show the bus garage,
Harry Hoag front, and high school addition.


June 1 photos ( bus garage, Harry Hoag front)
  
May 19 photos (Hoag front, bus garage,
Hoag interior)


May 5 photos (high school, Hoag front, parking
lot/garage)
  
April 27 photos (traffic pattern, Harry Hoag
front, bus garage)
April 13 photos
FIRST ROW: Harry Hoag parking lot, bus garage, school front
SECOND ROW: Inside Harry Hoag, Harry Hoag hallway, high school
addition
  
  
March 23 photos ( Harry Hoag front,
offices at Hoag)
  
March 10 photos (high school, Harry Hoag school,
bus garage)
  
Progress to Feb. 16
--- Steel for the bus garage is going up
---Heating units inside the high school addition are being installed
---At Harry Hoag, the back wall has been removed, site work at the
front of the school is progressing well. The lack of snow has helped
outside work considerably.
--- It is hoped that the new windows will arrive before the April
Spring break
--- Overall, the project is going very well.
TOP
Progress to Jan. 5
----Steel is up at the high school addition -
waiting for roof decking
---- A committee is working with fitness consultant Jim LaFountain
concerning the design of the new physical therapy and fitness
center
----The playground committee continues work on playscape designs
----Bus garage foundation is poured- waiting for steel to arrive
----Inside work at Hoag progressing well
Progress to Dec. 1
----The foundation for the high school
addition is in
----Two-thirds of the footers for the bus garage have been poured;
excavation continues in the back hill
----Drainage work by the kindergarten wing is complete, solving a
longstanding problem
----Front entrance to Harry Hoag school is almost ready to be torn
off
----Work continues on the entrance to the school, a new flagpole
will be installed
---- The playground committee visited four districts to get ideas
for equipment at Hoag
*** The project is moving right along, helped by
warmer than normal weather in November
Progress to Nov. 18
---- Concrete has been poured for the walls of
the high school addition
---- Excavation continues at the bus garage site, footings are being
prepared
---- The roof at Harry Hoag is finished
with only detail work to go.
---- Footing for the new sign at Hoag is in with brick work underway
---- Playground committee is visiting nearby communities to help
them make a decision on new playground equipment at Hoag
---- Forms for footings of the new front at Hoag are being
installed
---- Work on drainage at the kindergarten wing is expected to be
complete in a week.
**** The work is progressing ahead of
schedule!!!
September 30 photos (garage
demolition, site work )


Capital
project bids awarded
At its July 29 special meeting, the Board of Education
awarded bids totaling $12.8 million for the capital construction
project approved by school district voters in February, 2008.
Putrelo Building
Enterprises Inc. was awarded the general construction contract in
the amount of $6.7 million. Additionally, Putrelo received alternate
awards of $9,000 for window covering treatment and $36,000 for wall
tile work in Harry Hoag Elementary School.
Central New York Construction was awarded the contract for site work
in the amount of $1,669,500 plus alternates of $112,000 to resurface
the running track and $28,690 for additional drainage work at Harry
Hoag Elementary School.
The school board awarded other
bids as follows:
• Roofing: S & L Roofing and Sheetmetal, Inc., $1,549,000
• Electrical: Schenectady Hardware & Electrical Co., Inc.,
$1,330,000
• Heating, Ventilating, and Air Conditioning: DiGesare Mechanical,
Inc., $868,000
• Plumbing: Merit Plumbing & Heating LLC, $477,000
Superintendent of Schools Douglas Burton said that even
with the alternates, the total bids came in about $200,000 under the
projected total construction cost.
The project includes a new transportation
facility; a number of educational, structural and energy
improvements at Harry Hoag; reconfigured traffic loop and parking at
Hoag; a three-room addition at the Junior/Senior High School; and
replacement of the West Street steps.
One interesting aspect of roof repair and construction
at each school is the inclusion of solar panels that will be
anchored to the steel in the roofs. These panels will not only
enable the district to reduce its energy costs, but will also be
used as a teaching tool in science classrooms. Students will be able
to monitor the panels via computer to observe and measure how well
the panels are working.
top of page
pdf of Capital Project
brochure
Back to District Home Page
|